Construction continues to move forward on Phase One, including:
- Installing underground utilities, and beginning to waterproof, insulate and backfill the foundation walls to complete the prayer garden foundation.
- Creation of doorways from old prayer room to the new east-west corridor.
- Framed new student stage and finishing masonry for the new doorway from the student space to the east patio area.
- Removed all of the old gym lighting and beginning work on the new lighting for the student space.